PRODUCTION PLAN
Week 3 – October 23-30, 2006 - Research |
|
|
hared
- Research Competitive Environment
Producer
- Finish Production Schedule
- Rough Draft of Project Overview
Art Director
- Begin Roughs for Presentation Template
- Review Existing Source Imagery/Fonts
- Rough Draft of Creative Brief
Content Director
- Rough Draft of Site Map
- Initial Assessment of Site Content
Technical Director
- Rough Draft of Technical Requirements and File Naming Conventions
- Record any Technical Issues/Requirements/Client Questions |
|
|
|
|
|
Week 4 & 5 – November 6 -13, 2006 - Design |
|
|
Shared
-Design Document Compiled
-Design Document Presented
-Images Scanned and Formatted
-Team Creates Individual Comps (Site Prototype)
-Team Decides on Creative Direction
Producer
- Site Prototype
- Project Overview
Art Director
- Site Prototype
- Creative Brief
- Project Schedule
Content Director
- Site Prototype
- Site Map, Content Inventory
- Site Content Research
Technical Director
- Site Prototype
- Technical Requirements |
|
|
|
|
|
Week 6 & 7 – November 20 - 27, 2006 - Production |
|
|
Shared
-Coding
-Image Slicing
-Revisions are Made Based on Client feedback
-Presentation to Other Constituents
-Beta Site |
|
|
|
|
|
Week 8 & 9 – December 4 -11, 2006 - Post-Production |
|
|
Shared
-Site is Uploaded to Server and Presented
-Final Presentation to Client |
|
|
|
|